en+90 232 445 01 24
·
info@ogislaw.com

Do cancellation rights under voyage charterparty survive re-nomination of load port?

St Shipping & Transport Inc v. Kriti Filoxenia Shipping Co SA [2015] EWHC 997 (Comm) (MT Kriti Filoxenia)

The Commercial Court has considered whether cancellation provisions in the BEEPEEVOY3 charterparty form were applicable in the event of re-nomination of a load port by charterers under the charter. In this case, the Charterers re-nominated the load port which the Owners were not able to reach by the cancellation date. The Charterers cancelled the charterparty. In arbitration proceedings, the Tribunal found that the cancellation provisions were not applicable where the Charterers had exercised the contractual option to re-nominate a load port. The Charterers appealed the decision to the Commercial Court, which upheld the findings of the Tribunal and dismissed the appeal.
The background facts

This case concerned a voyage charterparty under the BEEPEEVOY 3 standard form. The key clauses in the charterparty provided as follows:

“17.… If it appears to Charterers that the Vessel will be delayed beyond the Cancelling Date Charterers may require Owners to notify Charterers of the date on which they expect the Vessel to be ready to load whereupon Charterers shall have the option to cancel this Charter…

24.… If after any loading or discharge port or place has been nominated Charterers desire to vary such port or place, Owners shall issue such revised instructions as are necessary at any time to give effect to Charterers’ revised orders and any period by which the steaming time taken to reach the alternative port or place exceeds the time which should have been taken had the Vessel proceeded thither directly shall count as laytime or, if the Vessel is on demurrage, as demurrage.”

The vessel proceeded to a nominated load port within the range provided for under the charterparty. The Charterers then nominated an alternative load port under clause 24. The Owners could not reach that load port by the cancellation date and the Charterers cancelled the charterparty in reliance upon clause 17. The Owners denied that the Charterers had a right to cancel and accepted the cancellation as a repudiation of the charterparty. The dispute went to arbitration.

The arbitration award

The Tribunal found in favour of the Owners and held that the cancellation provisions in clause 17 did not apply where the Charterers exercised the liberty given under clause 24 to re-nominate the load port. The Tribunal further held that, even if the cancellation provisions did apply, the Charterers may not cancel where the re-nomination was made at a time when the estimated time of arrival for the re-nominated port was after the cancellation date under the charterparty. The Charterers appealed to the Commercial Court.

The Commercial Court decision

When it came to construing the words in clauses 17 and 24 of the charterparty, the Court took as its starting point the ordinary and natural meaning of the words used in those clauses as they would be understood by reasonable charterers and owners in the context in which the agreement was made. The Court highlighted the importance of the fact that the parties to a charterparty were involved in a venture which required a degree of co-operation in order to work successfully. Regarding clause 17, the cancellation clause, the Charterers’ ability to cancel necessarily entailed that the Charterers would do what is necessary on their part to enable the vessel to achieve that cancellation date and not impair the Owners’ ability to comply with that date.

The Court also looked at the reasons why it is in the interests of both sides to agree a cancellation date. At common law, subject to the express terms of a charterparty, both parties are bound by the contract until the delay is such that it frustrates the commercial purpose of the venture. Agreeing a cancellation date provides certainty to both parties in that it avoids disputes as to when that delay has frustrated a contract, which is a matter of fact in each case.

The Court referred to the “broad commercial interpretation” it has previously taken in the construction of these types of clauses, in order to achieve the parties’ commercial objectives. In this regard, the Court examined the commercial considerations which underlie the re-nomination clause. For the Charterers, the main advantage of this clause is to have greater flexibility to revise their orders so as to tailor their shipping arrangements according to their cargo arrangements. On the other hand, absence of the load port re-nomination provision would be advantageous to the Owners since it would give them the certainty of an irrevocable nomination. The Court also noted the commercial value of the cancellation clause from the Charterers’ perspective. On balance, the Court placed more importance on the Owners’ concerns of losing the certainty of an irrevocable nomination, whilst at the same time remaining exposed to the Charterers’ right to cancel.

The Court also noted that clause 24 made no express reference to the cancellation rights under clause 17. The Court recognised that the BEEPEEVOY 3 charterparty, being a standard form, is a document drafted with considerable care. Had the draftsmen of this form intended for the clause 17 cancellation rights to apply to a re-nomination of the load port under clause 24, express words would have been used to that effect and would have provided for how such rights would apply and in what circumstances. No such words were present in this case.

The appeal was therefore dismissed.

Comment

This case serves as a useful reminder of the English Court’s approach to the interpretation of charterparty provisions and, in particular, to consideration of the interplay between a cancellation clause and a load port re-nomination provision under a voyage charterparty. This decision also highlights the Court’s commercial approach to such issues, in particular its reference to the Charterers’ duty to co-operate with the Owners and to do what is necessary to enable the vessel to achieve the cancellation date if they wish to be able to rely upon the cancellation clause.

Source: http://incelaw.com